ADU construction: cost, permits and timelines

A detached ADU in Southern California runs $220,000 to $385,000 for a 600–1,000 sq ft unit and takes seven to eleven months. A garage conversion starts near $95,000. A junior ADU inside the existing house is the cheapest path of all.

Those are our real numbers, not a range scraped off a national average. Below is what each type costs, what moves the number up or down, how long each phase actually takes, and what happens at the permit counter in your city.

We design it, engineer it, submit it, answer the correction letters and build it. One licensed contractor from the first site visit to the certificate of occupancy.

What an ADU costs to build

Priced by unit type. The per-square-foot figure falls as the unit gets bigger — the kitchen, bathroom and utility connections cost roughly the same whether the unit is 500 sq ft or 1,000.

TypeTypical sizeCost rangePer sq ftTimeline
Junior ADU (JADU)Up to 500 sq ft $90,000 – $150,000$210 – $3203 – 5 months
Garage conversion350 – 500 sq ft $95,000 – $165,000$210 – $3304 – 6 months
Prefab / modular400 – 800 sq ft $150,000 – $280,000$230 – $3605 – 8 months
Attached ADU500 – 800 sq ft $170,000 – $290,000$255 – $3756 – 9 months
Detached ADU600 – 1,000 sq ft $220,000 – $385,000$290 – $4307 – 11 months

The four types, and which one fits your lot

Most homeowners arrive knowing they want “an ADU” without knowing there are four different things that word covers. They are not interchangeable, and the right one usually comes down to your lot, not your preference.

Detached ADU

A standalone building in the yard with its own entrance, kitchen and bathroom. The most expensive and the most valuable — it rents as a real home and appraises as one. Needs enough open yard to meet setbacks and a route for equipment to get back there.

Attached ADU

Built onto the existing house, sharing one wall but with a separate entrance and full kitchen. Cheaper than detached because one wall and part of the foundation already exist. Good on narrow lots where a standalone unit will not fit the setbacks.

Junior ADU (JADU)

Carved out of the existing house, capped at 500 sq ft, with an efficiency kitchen. The fastest and cheapest route. It can share a bathroom with the main house, which is what keeps the cost down. Often a converted bedroom with an exterior door added.

Garage conversion

Turning an existing garage into permitted living space. The slab and walls are already there, so you are paying for insulation, systems and finishes rather than structure. Whether your city still requires replacement parking is the question that decides the budget.

See full garage conversion pricing →

What we actually build

A 750 sq ft detached unit on a 25′ × 30′ footprint — the size that fits most standard lots while still working as a genuine two-bedroom home.

B 1 C 12 6 TOP PLATE FINISHED FLOOR 8'-0" 14'-9" 25'-0" FINISHED GRADE 1 2 5 6 FRONT ELEVATION Gable end · entry D E F D TOP PLATE FINISHED FLOOR 8'-0" 30'-0" 3 4 7 8 9 SIDE ELEVATION Eave wall · utilities KEYNOTES 1 Class A composition shingle over synthetic underlayment 2 7/8" three-coat stucco over two layers Grade D paper 3 Wood roof trusses at 24" on centre 4 R-38 ceiling / R-21 wall, Title 24 compliant 5 Screened gable-end attic vent, per code 6 2x6 fascia with continuous vented soffit 7 Dual-glazed vinyl windows, per Title 24 8 Sub-panel from main service, load calc req. 9 Slab-on-grade, continuous footing per structural NORTHCRAFT BUILDERS · TYPICAL DETACHED ADU ILLUSTRATIVE — NOT FOR CONSTRUCTION CONDITIONED AREA 750 SQ FT FOOTPRINT 25'-0" × 30'-0" OCCUPANCY 2 BED / 1 BATH PLATE HEIGHT 8'-0" ROOF PITCH 6:12 OVERALL HEIGHT 14'-9" ABOVE GRADE
Typical detached ADU. 8′ plate, 6:12 roof, 14′-9″ to the ridge — under the 16-foot height limit most California cities apply to detached units, which keeps it out of the exceptions process.

What moves the number

Two identical 750 sq ft units on two different lots can be $80,000 apart. Here is where that gap comes from, roughly in order of how much it matters.

VariableWhat it doesTypical swing
Electrical service If the main panel cannot carry another dwelling, you need a sub-panel and often a service upgrade from the utility. $6,000 – $12,000
Sewer and water runs Distance from the unit back to the existing laterals. Long trenches through finished hardscape get expensive fast. $4,000 – $18,000
Site access Whether an excavator and a concrete truck can reach the back yard, or everything comes through a side gate by hand. Up to 15%
Slope and soils A flat pad needs a standard footing. A slope may need retaining, deeper footings or a geotechnical report first. Up to 18%
Finish level Cabinets, counters, flooring and fixtures. The single largest thing you actually control. Up to 30%
Design review Cities with objective design standards or a historic overlay add drawing time and a review cycle. $4,000 – $9,000

How long an ADU takes

The part that surprises people: design and plan check take about as long as building the thing. Nobody is on your lot for the first three to five months.

  1. Feasibility and site check

    We confirm the unit fits your parcel under setbacks, height and coverage before you spend anything on design.

    1 – 2 weeks
  2. Design and drawings

    Floor plan, elevations, selections. This is where you make the decisions that set the budget.

    4 – 8 weeks
  3. Structural and Title 24

    Engineering and the energy compliance package, produced alongside the architectural set.

    2 – 3 weeks
  4. Plan check submittal

    Submitted to your city. Then you wait for the first round of comments.

    4 – 8 weeks
  5. Corrections and resubmittal

    We answer the correction letter and resubmit. Most sets take one round; some take two.

    2 – 6 weeks
  6. Foundation and framing

    Permit issued, ground broken. The unit goes from a hole to a weather-tight shell.

    4 – 6 weeks
  7. Rough systems and inspections

    Electrical, plumbing and mechanical roughed in, then inspected before anything gets covered.

    3 – 4 weeks
  8. Insulation, drywall, finishes

    The longest build phase. Insulation, drywall, cabinets, flooring, fixtures, paint.

    6 – 10 weeks
  9. Final inspection and sign-off

    Final walk-through with you, punch list, then final inspection and the certificate.

    1 – 2 weeks

What the price includes

The line that separates an honest bid from a low one is usually what got left out of it. Here is ours.

Included in every ADU we quote

  • Architectural drawings and the full permit set
  • Structural engineering and Title 24 compliance
  • Permit submittal and every correction letter answered
  • Foundation, framing, roofing and exterior finish
  • Electrical, plumbing and mechanical, roughed and finished
  • Insulation, drywall, paint, flooring and trim
  • Kitchen and bathroom cabinets, counters and fixtures
  • All inspections through final sign-off
  • Workmanship warranty in writing

Quoted separately, because it varies

  • City permit and impact fees, paid at issuance
  • School fees where the city levies them
  • Utility service upgrades charged by the utility
  • Geotechnical report, if your city or slope requires one
  • Landscaping and hardscape beyond the unit
  • Solar, where a new dwelling triggers it
  • Appliances
  • Furniture and window coverings

The permit process, honestly

Every ADU needs a permit. There is no version of this where you skip it — an unpermitted unit cannot be legally rented, will not appraise, and becomes the buyer's problem when you sell.

We submit, not you

The drawings go in under our licence. When the correction letter comes back, it comes to us and we answer it. You never stand at a counter.

State law sets the floor

California law requires cities to review a conforming ADU application ministerially — no public hearing, no neighbour vote. Your city fills in the rest.

Your city fills in the rest

Setbacks, height, objective design standards, fire-zone requirements and how the utility handles a new meter. This is where projects actually stall, and it differs across all 134 cities we cover.

We do not publish statute numbers we have not checked. California ADU law has changed nearly every year since 2017 and city ordinances move on their own schedule. Requirements vary by jurisdiction — confirm current rules with your building department before relying on anything you read here.

Where we build ADUs

Every city has its own page with that city's setbacks, height limits, permit process and current plan-check timeline.

ADU questions, answered

How much does an ADU cost to build in California? +
A detached ADU runs $220,000 to $385,000 for a 600–1,000 sq ft unit in our area. Attached units run $170,000 to $290,000. A garage conversion starts near $95,000 and a junior ADU inside the existing house is the least expensive route at $90,000 to $150,000.
Can I build an ADU on my lot? +
Usually yes. State law makes ADUs allowable on most single-family and multifamily lots in California. What varies is size, height, setbacks and design standards, all set by your city. We check your specific parcel before you spend anything on design.
How long does an ADU take from start to finish? +
Seven to eleven months for a detached unit. Design and plan check account for three to five of those months, which is longer than most people expect. The build itself is typically four to six months.
Does an ADU add value to my property? +
A permitted ADU is counted as living area and appraises as such. An unpermitted one does not, cannot be legally rented, and becomes a disclosure problem at sale. That gap is the main reason we will not build without a permit.
Do I need a separate electrical meter? +
Not always. Many ADUs run off a sub-panel fed from the existing main service. Whether that works depends on your panel capacity and a load calculation, which we run during design. A separate meter is a utility decision and gets quoted separately.
Can I build an ADU and rent it out? +
Yes, once it is permitted and has final sign-off. Short-term rental rules differ city by city, so check yours before you plan around nightly rates. Long-term rental is broadly permitted statewide.
What if my yard has no side access? +
It is still buildable, it just costs more. Materials come through the house or over the fence, and we use smaller equipment. Expect roughly a 15% premium on a tight-access site, which is why it is one of the first things we look at.
Do you handle the permit, or do I? +
We do. Drawings go in under our licence, correction letters come to us, and we schedule and attend every inspection through final sign-off.